Before you begin
What you need to check the solar grant
Use the exact kWp from the quote, not the panel count alone.
Enter your supplier’s export payment and import rate because their spread drives payback.
Reading the answer
Understanding your grant and payback
Payback combines avoided imports and paid exports. It is not a guarantee of future tariff values.
A battery can increase self-consumption while also increasing capital cost enough to lengthen payback.
Boundaries
Assumptions and limitations
Working assumptions
- Grant: €700/kWp for the first 2 kWp and €200/kWp for the next 2 kWp, capped at €1,800.
- Generation uses 900 kWh/kWp/year before orientation adjustment, which is about 5% below the national mean PVGIS gives for a south-facing Irish roof.
- When no quote is entered, cost is estimated as €2,500 plus €1,100/kWp, and €3,000 more for a 5 kWh battery.
Where to be careful
- A professional yield estimate should model roof pitch, horizon, shading and local losses.
- Approval must be in place before work begins and an SEAI-registered company must be used.
Worked example
The same question, answered end to end
An eligible pre-2021 home pricing a 4.2 kWp south-facing array with no battery, nobody home during the day, importing at 36c and exporting at 20c, with no quote entered.
What was entered
- Eligible owner, home built and occupied before 2021, no previous solar grant on the MPRN.
- A 4.2 kWp array, south-facing with little shading, no battery.
- Nobody usually home during daylight hours.
- Importing at 36c per kWh, exporting at 20c. No installer quote entered.
How it is worked out
The grant is €700 per kWp on the first 2 kWp — €1,400 — plus €200 per kWp on the next 2 kWp — €400 — capped at €1,800.
With no quote entered, cost is estimated as €2,500 plus €1,100 per kWp: about €7,120.
Generation is 4.2 kWp × 900 kWh × 1.0 for a south-facing roof: about 3,780 kWh a year.
With nobody home in the day and no battery, 30% is used in the home and the rest exported — reduced slightly because the array is over 4 kWp.
Self-used units save 36c each; exported units earn 20c each. The two together are the annual value.
Payback is the cost after the grant divided by that annual value.
What the tool returns
- Estimated installed cost
- €7,120
- Cost after the grant
- €5,320
- Annual generation
- 3,780 kWh
- Simple payback
- 5.7 years
Common questions
Questions about this tool
How much is the domestic solar grant in 2026?
SEAI states €700 per kWp up to 2 kWp, then €200 per additional kWp up to 4 kWp, with a maximum of €1,800.
Does adding a battery increase the solar grant?
No standalone battery amount is added to this domestic solar-PV grant calculation.